Finally it has started

image

After two days of cleaning up. two trailer loads of rubbish and concrete

Finally after 7 months waiting time the site work has started on our new house.

Metricon has started work on 24th October with earth works as promised. To be honest this is the only thing they have done on time. Its an another story. We have been to the site almost everyday now.

24th October: Site start with scrape and leveling
25th October: Some new pegs, seems something has happened. but can’t figure out what!

image

27th October: We have electricity! Looks like some kind of piers has been installed and poured some concrete.

Our site supervisor Josh hasn’t called us yet, but it’s good to see something happening on the site.